Congratulations to Regions Bank and our team for a job well done in Lufkin, TX!!! A demolition/ground up banking facility of approximately 5,000 sq ft. The project duration was reduced from 180 days down to 102 as well as needing to overcome a major issue of removing 9 ft soils at the building pad on a very tight site in downtown Lufkin. Once complete, our build time for this branch was 89 days including demolition. We turned the project over December 1, 2016.